AFTER RAISING THE POWER RATES TO ALMOST 4 TIMES THE AMOUNT THIS IS WHAT IS HAPPENING;


POWER OUTAGES:
THURSDAY; 8-10PM
FRIDAY; 8-10PM
SATURDAY: 8-10PM
SUNDAY: 8-10PM
MONDAY: 9AM-11AM, 1PM-2PM, 8:36PM-10:30PM

CUC: Cylinder, turbocharger problems cause power outage Tuesday, 03 June 2008 00:00 By Raymond A. Martinez - Variety News Staff THIRTY percent of the island suffered power outage yesterday as two engines at Power Plant 1 experienced mechanical breakdown, leaving only two engines running to service the rest of the
communities.
This is according to Commonwealth Utilities Corp. Executive Director Antonio S. Muna.
Muna explained that engines #3 and 6 were down due to mechanical problems.
Engine #3, he said, experienced abnormal sound on its cylinder #16, while engine #6 was down due to presence of water in the turbocharger lube oil system.
CUC report says unit #3 needs valve replacement and unit #6 needs further inspection with its turbocharger cooler.
Engines #3 and 6 were secured yesterday, but are still under observation by the power plant crew.
Muna mentioned that engines #2 and 8 were the only power units that were operating yesterday with a combined capacity of 13 megawatts only.
CUC implemented load shedding from 8 a.m. until 12 midnight, affecting the entire grid of Kiyas 1 and 4, Feeders 7 and 4.
San Vicente, portions of Papago, Upper and Lower Dandan, Isley Field, Upper Gualo Rai, Chalan Kiya, Oleai, San Jose, Garapan, Koblerville, As Gonno, San Antonio, Capital Hill, Kagman, Achugao, San Roque, Afetnas and several other places were affected.
Water services and traffic lights were also down in yesterday’s power outage.
Last week CUC announced that high atmospheric temperature and overheating radiator has paralyzed two of its power plant engines which caused power service interruption island-wide.
Gary P. Camacho, CUC’s power division acting manager, said they will repair a defective air break system on Feeder 3 near the Gualo Rai intersection today.
“The repair of this equipment will allow the crews to isolate specific areas of the grid to perform systems maintenance and minimize future feeder outages,” Camacho explained.
Feeders 2 and 3 will be taken offline from 8 a.m. to 10 a.m.
Other Feeders that will be affected in today’s outage include Kiya 1: Second Partial, Feeder 1: Laterals, entire grids of Feeders 4 and 7, and entire grids of Kiyas 1,







Photo Sharing and Video Hosting at Photobucket

we're not gonna take it

ROLLING BLACK OUT"S

Photo Sharing and Video Hosting at Photobucket

OUTAGE November 19, 2007...lower dandan.

OUTAGE November 20th, schedule to go off in some parts of the Island.

OUTAGE November 21th, 2007 HITS KAGMAN

EMERGENCY BLACKOUT HITS SAIPAN November 21st, 2007 5pm without announcement.

ROTATING BLACKOUTS ARE BACK November 23rd, 2007
Feeder 4 - 1 in the morning and another from 7pm-9pm.

OUTAGE: November 25th, 2007
Feeder 4 - 1 at midnight and another at 7-9pm.

OUTAGE: November 26th, 2007
Susupe, Feeder 4 7-9pm & midnight for 2 hours.

OUTAGE: November 27th, 2007
Feeder 4 morning hours




Photo Sharing and Video Hosting at Photobucket
Photo Sharing and Video Hosting at Photobucket

HERE WE GO AGAIN

Local Sunday, March 30, 2008 Fate of power rate repeal now lies with Senate By Agnes E. Donato Reporter House members are counting on the Senate to pass a bill repealing a law that reduced power rates in the Commonwealth. Rep. Tina Sablan, one of bill's sponsors, said yesterday that passing the bill is a difficult political decision, but it “needs to be done.” “I am hopeful that they [senators] will see the gravity of the situation and act expeditiously,” Sablan said in an interview yesterday. Rep. Heinz Hofschneider, also a sponsor of the bill, expressed the same hope. “Everyday that we don't act to repeal that law means CUC will continue to burden the general fund,” he said. House Bill 16-79 passed the Lower House with a 17-1 vote on Thursday. Rep. Stanley T. Torres voted against the bill. Representatives Oscar M. Babauta and Ralph Torres were not present. The bill proposes to repeal Public Law 15-94, which forced power rates down to 17 cents per kWh in October 2007, and reduced or scrapped other charges for residential customers. The law, compounded by the rising cost of fuel, has caused the Commonwealth Utilities Corp. to face a shortfall of about $1 million each month for fuel alone. Due to the shortfall, CUC for instance failed to pay for a full 30-day fuel supply last month. Power outages are now occurring partly because CUC is stretching to last for 30 days the 23-day supply that it managed to purchase. Hofschneider said that the repealer bill would not only allow CUC to pay for full fuel deliveries, but also reduce government subsidy to the utility. In addition, Sablan argued, the customers would not lose much if P.L. 15-94 was repealed. The law, she noted, has not been of any real benefit to the customers, since emergency regulations were adopted to give CUC flexibility in setting the fuel component of the power rates. House Bill 16-79 will become law once approved by the Senate and signed by the governor. Photo Sharing and Video Hosting at Photobucket
Photo Sharing and Video Hosting at Photobucket http://home.myspace.com/index.cfm?fuseaction=user

Tuesday, November 20, 2007

Public Law 15-94 deception

st-Wednesday November 21, 2007 Letters to the Editor
Tuesday, November 20, 2007

To the Legislature:It is with such displeasure to inform you-our leaders-that deception in public office is a crime and is not tolerated lightly. We have spent well over five months pursuing what was good for the people of the CNMI and when we achieved it, something went drastically wrong. All of you had the opportunity to review our proposal of rate change on July 2 and 3, which the Senate president accepted as a working document toward H.B. 15-246, a bill to lower the rates introduced and authored by the minority leader Arnold Palacios. In our proposal we specifically requested further amendments be made, especially the removal of Section 18 thru 22 in the original House bill. The reason why we requested such an amendment is due to the fact that there was no Public Utilities Commission in place and the differences between the Executive branch and the legislative body on appointing a board was an issue hindering the process. At this point we do not believe that appointing anyone to the PUC board can be achieved because of the fact that no one in their right mind would dare take on such a responsibility since, in the end, he or she will be blamed for any wrong move. Although it is an honorable appointed position, we believe that one's credibility and integrity can be forever tarnished in the public view given the present situation of CUC. We are also mindful of the current high global fuel prices all over the world but that alone is not a basis as to why the people of the CNMI were deceived and taken advantage off. Furthermore, to you Mr. Arnold Palacios, we feel that you are the primary person responsible for this current situation we are faced now and we must seriously notify you that you have deceived the people of the CNMI, especially the voters. I respectfully urge you to prioritize CUC's shortfall as promised rather than concentrate on your speakership fight with Benavente. Concerning the speakership, we the people feel that none of you are qualified or even deserve to sit on such an honorable position. Therefore we recommend Congressman Stanley Torres to be Speaker of the House for he is a great leader who cares, understands that the people are suffering and he fights for the people. Gentlemen, we urge you to deliver and return what was promised to the people before the election. A home was burned down because of the use of candles and why is such a mishap happening near Christmas And New Year?

Gregorio S. Cruz Jr. President, Taotao Tano CNMI Association, Inc.

Outage hits Kagman

mv- Local Wednesday, November 21, 2007 By Ferdie de la TorreReporter

Kagman experienced an outage yesterday afternoon when the Commonwealth Utilities Corp. conducted repairs on the electrical wires and equipment that were damaged during Monday's strong rain and winds brought by a trade-wind disturbance.CUC linemen turned off the electric power in Kagman after school or at 3pm as they made the repairs.CUC spokesperson Pamela Mathis said electricity will be restored as soon as the lines are clear of danger.Mathis underscored the need to conduct such repairs before major power failures occur.In addition to Monday morning outages in southern Saipan, CUC also fixed damaged equipment in Dandan, Capital Hill, As Matuis, and Koblerville.A number of trees fell on high voltage lines and took the lines down in several locations during the heavy rains.There were isolated minor outages yesterday as CUC field crews made repairs.Mathis issued the following safety measures for the public to observe during heavy rains:- Customers and children should never touch a fallen power line and always call for help. Electricity may still flow through downed lines.- Parents should not allow children to play in wet trees that are anywhere near high voltage lines because the electricity can also flow through wet vegetation.- If power lines fall on vehicles, stay inside the car-never get out until the CUC personnel advises that it's safe.- Any time a home floods or fills with water, unplug all appliances or cords along the floors or baseboards.

Sunday, November 18, 2007

Chalan Kanoa house fire an accident CORRECTION "Chalan Laulau"

mv-Monday November 19, 2007

By Cherrie Anne E. Villahermosa
Variety News Staff



A fire that damaged a home in Chalan Laulau on Thursday evening was an accident, according to Department of Public Safety spokeswoman Lei Ogumoro.

She said a candle used to light the kitchen of a house, which had no electricity, was the cause of the fire that damaged the wood and tin structure.

Ogumoro said no one among the nine family members was hurt in the fire on early Thursday evening.

The candle in the kitchen was placed on a cooler and the family members — five adults and four children — were all outside when they saw their kitchen engulfed in flames.

They tried but failed to extinguish the fire.

Because the structure was made of plywood, the fire was able to spread rapidly throughout the house.

But firefighters dispatched to the scene were able to bring the fire under control and secure the area.

DPS said the incident has been classified as an accident.

The owners of the structure are Gregorio and Tricia Mettao.

CUC employee pleads guilty to misconduct

mv-Monday November 19, 2007


--------------------------------------------------------------------------------

CUC employee pleads guilty to misconduct

By Cherrie Anne E. Villahermosa
Variety News Staff



A COMMONWEALTH Utilities Corp. employee who was charged for stealing money from a customer has pleaded guilty to misconduct in public office.

Manuel Quitano Camacho, 42, appeared for a change of plea hearing on Friday before Associate Judge Kenneth L. Govendo.

Camacho was represented by attorney Brien Sers Nicholas.

Assistant Attorney General Mike Nisperos agreed to dismiss the theft by deception charge with prejudice in exchange for Camacho’s plea.

Govendo accepted the plea and sentenced Camacho to 60 days of imprisonment, all suspended, except for eight hours of time already served.

Camacho was also placed on probation for 18 months.

He will pay a fine of $500, an assessment fee of $25 and a probation fee to be determined by the Office of Adult probation.

Camacho will perform 100 hours of community work service and submit a letter of apology to CUC and to Charles Cepeda.

Camacho’s review hearing was set for March 13, 2008 at 9 a.m.

Camacho was charged for taking $1,622.61 from Cepeda.

According to the Attorney General’s Office, Camacho committed the illegal acts between Dec. 2006 and April 2007 as CUC’s administrative support assistant.

It was Charles Cepeda, general manager of Pacific Trading, who wrote a letter to CUC regarding several power billing transactions with Camacho.

Camacho received over $1,000 from Cepeda but did not forward the money to CUC.

Camacho said he used the money to purchase a new alternator for his truck.

Palacios says new power rates illegal

mv-Monday November 19, 2007


--------------------------------------------------------------------------------

Palacios says new power rates illegal

By Gemma Q. Casas
Variety News Staff



HOUSE Minority Leader Rep. Arnold I. Palacios says the emergency regulations allowing the Commonwealth Utilities Corp. to again charge higher power rates are “unlawful” as they disregard the existing law that fixes the rate at 17.6 cents per kilowatt hour.

Palacios, R-Saipan, one of the principal authors of House Bill 15-246, which later became Public Law 15-94 on Oct. 4 after the Legislature overrode Gov. Benigno R. Fitial’s veto, said the executive branch has no power to alter what was set in P.L. 15-94 in the absence of a Public Utilities Commission.

“Because the commission has yet to convene, it is not possible for any rate increase to be reviewed and approved in accordance with law. Therefore, CUC has acted beyond its authority, and the notice of Nov. 11 is void,” Palacios wrote the governor on Nov. 16.

“As a result, CUC is now imposing an unlawful charge on residential customers,” he added.

The emergency regulations took effect on Nov. 2 and will last for 120 days. CUC will then adopt them permanently.

CUC is now charging residential customers 25.8 cents for the first 1,000 kwh of energy they consume and 30.2 cents per kwh in excess of that.

The governor said the emergency regulations are allowed by P.L. 15-94 which states that the government can adjust prices of electricity based on the actual cost of imported fuel.

“We’re only complying with the law,” he said in an earlier interview with Variety. “We didn’t create the law. The cost of fuel was allowed by that law to be factored into the rates that we now have. The emergency regulations were also a function of that law that we promulgated.”

But Palacios said the power to adjust electric rates is specifically entrusted to the yet-to-be-formed Public Utilities Commission.

“Simply put, that intent is to require that any future rate changes be approved by a duly formed and convened Public Utilities Commission,” he added.

Wednesday, November 14, 2007

Funding hike for utility aid program

Local Thursday, November 15, 2007 By Agnes E. DonatoReporter

Gov. Benigno R. Fitial has signed into law legislation that increases funding for the government's utility aid program.The new law earmarks $300,000 from the Tobacco Control Fund revenues for a supplemental account to the Low Income Home Energy Assistance Program.The new legislation took into effect retroactively to Oct. 1, 2007.Public Law 15-110 was enacted in a bid to help local residents in paying for power bills. Low-income families can apply for the supplemental aid for the portion of their CUC bills not covered by the LIHEAP subsidy.The Department of Community and Cultural Affairs will manage the funds.The Legislature noted that, although LIHEAP provides assistance to low-income consumers, the aid does not cover the full amount of most Commonwealth Utilities Corp. billings.As a result, many-low income families have had their power supply disconnected for non-payment.Nearly 450 residents are receiving financial assistance under LIHEAP, a federal program. This number was reduced from almost 700 a year ago due to utility disconnections.“The creation of a LIHEAP supplemental account from Tobacco Control Fund revenues will assist low income families in paying CUC bills in excess of the LIHEAP subsidy. This will ensure that vital power and water services remain connected, and that the health of low-income families is not jeopardized by the rise in power rates in the Commonwealth,” the Legislature states in the legislation.

Fitial says Legislature allowed him to increase power rates

111507 Gemma Q. Casas Variety News Staff

GOVERNOR Benigno R. Fitial yesterday said the Legislature’s override of his veto of the measure lowering residential power rates still stands as law but his team of legal experts determined they can promulgate emergency regulations.
“I think this whole issue is being misunderstood,” he said. “The Legislature passed a bill that reduced (residential power) rates. But it says, as you know, that there should also be fluctuating rates in the event that the price of fuel goes up. As you know, the price of fuel went up. Now, it’s approaching $100 per barrel,” said the governor.
He vetoed House Bill 15-246 on Sept. 14 which sets the rate at 17.6 cents the first 1,000 kilowatt hours of energy residential customers use and 22 cents per kilowatt hour for anything in excess of that.
But both houses of the Legislature overrode it just before the Nov. 3 election.
Thus, H.B. 15-246 became Public Law 15-94 and took effect on Oct. 4.
Fitial said P.L. 15-94 also states in part: “The electric charges and rates in this section shall supersede and replace the residential rates established by the amendments to part 24 of the Electric Service Regulations of the Commonwealth Utilities Corp. as set forth in 28 Com. Reg. 9 26156, et se. (Sept. 27, 2006), which became effective on Oct. 27, 2006; provided that the electric fuel rates may fluctuate depending on the actual cost of fuel.”
Changes in utility rates can only be made by the Commonwealth Public Utilities Commission.
Pending the creation of the commission, the Legislature enacted a law allowing the attorney general to act as the quasi-body of CUC.
On Nov. 2, Fitial approved the Commonwealth Utilities Corp.’s emergency regulations allowing it to charge residents 25.8 cents per kwh for the first 1,000 kwhs and 30.2 cents per kwh for all electricity they consume over 1,000 kwhs.
“That law, which was overridden by the Legislature, allows for the fluctuating rates. We’re only complying with the law. We didn’t create the law. The cost of fuel was allowed by that law to be factored into the rates that we now have,” said the governor.
“The emergency regulations were a function of that law that we promulgated,” he added.

.

.

.

.

TAOTAO TANO PROPOSAL PAGE 1

TAOTAO TANO PROPOSAL PAGE 1

TAOTAO TANO PROPOSAL PAGE 2

TAOTAO TANO PROPOSAL PAGE 2

RESEARCH DONE AUGUST - SEPTEMBER 2007