AFTER RAISING THE POWER RATES TO ALMOST 4 TIMES THE AMOUNT THIS IS WHAT IS HAPPENING;


POWER OUTAGES:
THURSDAY; 8-10PM
FRIDAY; 8-10PM
SATURDAY: 8-10PM
SUNDAY: 8-10PM
MONDAY: 9AM-11AM, 1PM-2PM, 8:36PM-10:30PM

CUC: Cylinder, turbocharger problems cause power outage Tuesday, 03 June 2008 00:00 By Raymond A. Martinez - Variety News Staff THIRTY percent of the island suffered power outage yesterday as two engines at Power Plant 1 experienced mechanical breakdown, leaving only two engines running to service the rest of the
communities.
This is according to Commonwealth Utilities Corp. Executive Director Antonio S. Muna.
Muna explained that engines #3 and 6 were down due to mechanical problems.
Engine #3, he said, experienced abnormal sound on its cylinder #16, while engine #6 was down due to presence of water in the turbocharger lube oil system.
CUC report says unit #3 needs valve replacement and unit #6 needs further inspection with its turbocharger cooler.
Engines #3 and 6 were secured yesterday, but are still under observation by the power plant crew.
Muna mentioned that engines #2 and 8 were the only power units that were operating yesterday with a combined capacity of 13 megawatts only.
CUC implemented load shedding from 8 a.m. until 12 midnight, affecting the entire grid of Kiyas 1 and 4, Feeders 7 and 4.
San Vicente, portions of Papago, Upper and Lower Dandan, Isley Field, Upper Gualo Rai, Chalan Kiya, Oleai, San Jose, Garapan, Koblerville, As Gonno, San Antonio, Capital Hill, Kagman, Achugao, San Roque, Afetnas and several other places were affected.
Water services and traffic lights were also down in yesterday’s power outage.
Last week CUC announced that high atmospheric temperature and overheating radiator has paralyzed two of its power plant engines which caused power service interruption island-wide.
Gary P. Camacho, CUC’s power division acting manager, said they will repair a defective air break system on Feeder 3 near the Gualo Rai intersection today.
“The repair of this equipment will allow the crews to isolate specific areas of the grid to perform systems maintenance and minimize future feeder outages,” Camacho explained.
Feeders 2 and 3 will be taken offline from 8 a.m. to 10 a.m.
Other Feeders that will be affected in today’s outage include Kiya 1: Second Partial, Feeder 1: Laterals, entire grids of Feeders 4 and 7, and entire grids of Kiyas 1,







Photo Sharing and Video Hosting at Photobucket

we're not gonna take it

ROLLING BLACK OUT"S

Photo Sharing and Video Hosting at Photobucket

OUTAGE November 19, 2007...lower dandan.

OUTAGE November 20th, schedule to go off in some parts of the Island.

OUTAGE November 21th, 2007 HITS KAGMAN

EMERGENCY BLACKOUT HITS SAIPAN November 21st, 2007 5pm without announcement.

ROTATING BLACKOUTS ARE BACK November 23rd, 2007
Feeder 4 - 1 in the morning and another from 7pm-9pm.

OUTAGE: November 25th, 2007
Feeder 4 - 1 at midnight and another at 7-9pm.

OUTAGE: November 26th, 2007
Susupe, Feeder 4 7-9pm & midnight for 2 hours.

OUTAGE: November 27th, 2007
Feeder 4 morning hours




Photo Sharing and Video Hosting at Photobucket
Photo Sharing and Video Hosting at Photobucket

HERE WE GO AGAIN

Local Sunday, March 30, 2008 Fate of power rate repeal now lies with Senate By Agnes E. Donato Reporter House members are counting on the Senate to pass a bill repealing a law that reduced power rates in the Commonwealth. Rep. Tina Sablan, one of bill's sponsors, said yesterday that passing the bill is a difficult political decision, but it “needs to be done.” “I am hopeful that they [senators] will see the gravity of the situation and act expeditiously,” Sablan said in an interview yesterday. Rep. Heinz Hofschneider, also a sponsor of the bill, expressed the same hope. “Everyday that we don't act to repeal that law means CUC will continue to burden the general fund,” he said. House Bill 16-79 passed the Lower House with a 17-1 vote on Thursday. Rep. Stanley T. Torres voted against the bill. Representatives Oscar M. Babauta and Ralph Torres were not present. The bill proposes to repeal Public Law 15-94, which forced power rates down to 17 cents per kWh in October 2007, and reduced or scrapped other charges for residential customers. The law, compounded by the rising cost of fuel, has caused the Commonwealth Utilities Corp. to face a shortfall of about $1 million each month for fuel alone. Due to the shortfall, CUC for instance failed to pay for a full 30-day fuel supply last month. Power outages are now occurring partly because CUC is stretching to last for 30 days the 23-day supply that it managed to purchase. Hofschneider said that the repealer bill would not only allow CUC to pay for full fuel deliveries, but also reduce government subsidy to the utility. In addition, Sablan argued, the customers would not lose much if P.L. 15-94 was repealed. The law, she noted, has not been of any real benefit to the customers, since emergency regulations were adopted to give CUC flexibility in setting the fuel component of the power rates. House Bill 16-79 will become law once approved by the Senate and signed by the governor. Photo Sharing and Video Hosting at Photobucket
Photo Sharing and Video Hosting at Photobucket http://home.myspace.com/index.cfm?fuseaction=user

Wednesday, October 24, 2007

CONSUMER CONCERN!!!

Saipan Tribune Letters to the Editor By Agnes E. DonatoReporter
Friday, October 12, 2007

CUC water meter installation

As a concerned citizen I am writing this letter to simply ask the following questions that I personally believe would affect CUC water customers in general.On Oct. 8, 2007, the existing four water meters installed within our property was relocated and replaced with new ones outside our property line.The four relocated water meters were previously equipped with ¾ PVC ball valves but, to my surprise, these same ball valves were not reinstalled. The contractor explained that it is not part of their construction contract with the CUC Water Task Force.The technical and logical questions are:1. Why was no ball valve or gate valve installed after each water meter?2. How can the water customers repair their water pipe lines or plumbing fixtures if such valves are not provided?3. Will water customers need to call CUC water division if repairs are needed? If so, how soon will the water crew arrive at the customer's place? If the repair work takes one hour, one day or so, will CUC come and wait until the repairs are done? Who will be responsible for the lost or wasted water while waiting for the CUC crew(s)? There is a new 1 ½ PVC ball valve controlling the four new water meters installed at my place. I was told to close it to conduct repairs, resulting in the stoppage of water supply to the three other water meters. Is that logical?4. Is it not part of the contract with CUC/Water Task Force to have those ball valves/gate valves installed? (At least those with existing ball valves/gate valves prior to installation of new water meters.)5. If it is not part of the contract, then it may be part of the restoration clause of existing improvements damaged by construction operations (the installation of new water meters)?Please assist me to clarify this matter. Thank you very much.Manny T. VilagaIsa Road, Capital Hill

No comments:

.

.

.

.

TAOTAO TANO PROPOSAL PAGE 1

TAOTAO TANO PROPOSAL PAGE 1

TAOTAO TANO PROPOSAL PAGE 2

TAOTAO TANO PROPOSAL PAGE 2

RESEARCH DONE AUGUST - SEPTEMBER 2007